2014
November
Metalloinvest commenced pilot production at its oxygen station with a cryogenic air separation unit (ASU #3) at OEMK.
October
Coke Oven Battery #6, a key part of Metalloinvests investment programme, has come into operation at Ural Steel.
October
Metalloinvest entered the active phase of installation works for HBI-3 Plant (HBI-3) at Lebedinsky GOK, which will have an annual production capacity of 1.8 million tonnes.
May
Fitch Ratings upgraded Metalloinvests credit rating from BB- to BB with a stable outlook.
March
Metalloinvest signed a pre-export financing deal with a club of international banks, including Deutsche Bank, ING, Société Générale, BNP Paribas, Credit Agricole CIB, UniCredit Bank, BTMU and Credit Suisse.
February
Standard & Poors upgraded Metalloinvests long-term rating from BB- to BB with a stable outlook.